THE VISION
 
     
 
learning how to live in new relationship with each other…
to discover new ways of being healthy, vital and life-sustaining…
becoming a place where anyone can gather in community…
 
     
 
THE REBUILD PLANS
 
     
  The rebuild plans intend to maintain the character of the current site as much as possible and remove the vehicle traffic and parking from the activity areas. The prime goal of the rebuild project is to ensure the site is safer and enabled to operate more efficiently with the buildings reflecting the LEED® Green Building construction standards.  
     
 
 
   
 
Site development will be enhanced to take advantage of the waterfront to ensure that activities are focused in this area. The waterfront area will have an increased swimming area to include a new dock and swimming platform.

Plans to create a “wide game” area will provide more opportunities for growth and experience for those attending Hurlburt.

 
     
 
 
   
  The number of beds will be increased from 60 to 88. Facilities for showers and washrooms will be expanded to meet current and future needs. And the establishment of a multi-purpose facility will provide optimal space for meals and activities including space for crafts. This area will also be constructed as an all-season building with accommodations for up to 28 overnight guests, which will be made available for corporate, private and special events.

All facilities in the rebuild project will reflect our core values for living in sustainable building environments and will incorporate LEED® Green Building construction standards in the design plans.

 
     
     
  Proposed Timelines  
     
 
Construction Commences February, 2010
Construction Stops June 15, 2010
Construction Re-Commences September 15, 2010
Demolish Old Centre Building September, 2010
Official Opening of Rebuild Hurlburt 2011
 
     
  Proposed Financial Targets  
     
 
Community Support (including Gifts in Kind)
$
1,500,000
 
Foundations/Grants
$
500,000
 
Camp Hurlburt Alumni
$
500,000
 
Special Events/Projects
$
150,000
 
United Church of Canada
$
150,000
 
 
   
  Preliminary Construction Budget  
     
 
Item Unit
Amount
 
Main Hall 5719sf
$
1,715,700
 
Staff Cabin 1116sf
$
223,200
 
Single Cabins 713sf
$
142,600
 
Double Cabins 1403sf
$
280,600
 
Storage Building 700sf
$
70,000
 
   
 
Site Development 15000sf
$
150,000
 
Landscaping 5000sf
$
25,000
 
   
 
Utilities 1
$
0
 
Demolition 1
$
40,000
 
Wharf 1
$
40,000
 
Survey 1
$
12,000
 
Permits and DCC 1
$
55,000
 
Consulting Fees 1
$
301,631
 
Contingencies  
$
274,210
 
  Total:
$
3,329,941
 
 
     